Battery vision backup booster

  • Switch on circuit breaker Utility supply and load

LED for grid side voltage (top left) lights up red

  • Switch on circuit breaker Inverter Grid and Inverter Backup
  • Starting Inverter vision three and Battery vision

When the inverter starts, the LED for voltage on the backup path (top right) lights up red.

  • Change the slide switch from "Manual" to "Automatic"

The changeover switch turns to the left, the LED for power supply from the public grid (bottom left) lights up green.

Further steps:

Continue with test backup mode